|
Works in 2014
-
January, 2014
Installation works of the flotation line. Supply of equipment and installation works of the site with sludge dewatering for meat processing plant. Productivity of the line is 225 kg d. s. / hour.
-
February, 2014
Service of volute dewatering filter press. Productivity is 600 kg. d. s. / hour
-
March, 2014
Development of the central column of secondary settlers. Calculation of a design on durability and hydraulic work. The chief - installation of designs of columns.
-
April, 2014
Installation of sludge dewatering equipment at the poultry plant , with productivity 400 kg d. s. / hour
-
May, 2014
Presentation of the container with the membrane bioreactor (MBR) Average daily productivity is 25 m3 / day at the international exhibition "Aqua-Therm" in Kiev.
-
June, 2014
Reconstruction of wastewater treatment plants with productivity 59 000m3 / day. Delivery of the equipment. Installation of radial primarily settlers . - 2 pcs.
-
July, 2014
Commissioning of the radial primarily settlers. Installation of secondary radial settlers Ø30 and Ø28m.
-
August, 2014
Commissioning at wastewater treatment plants of mink farm with productivity 25 m3 / day Entering of the secondary radial settlers of siphon type in to operation.
-
September, 2014
Preparation works of the installation of an aeration system are completed.
-
October, 2014
Installation of the aeration system. Two four-in-line aeration tanks are filled and put into operation.
The layout of the bottom disc diffusers in the aeration tanks is 3808 pcs.
-
November, 2014
Compressor building. Installation works are at the final stage.
-
December, 2014
Reconstruction of the compressor building is at the final stage. Entering of blowers in to operation. Start of the commissioning.